GMove-In Command Center20 Gaudencio · Quezon City
6-day rescue planChecked 25 July 2026 · prices can move

Move in by July 31.
Buy less. Decide faster.

A couple-facing plan for turning an empty renovation into a safe, functional first home—without panic-buying permanent furniture or hiding unresolved site risks.

Default assumption: adults move first; Manu follows only after the child-safety gate passes. Change this in Decision 01.

01

Safety is not a bridge.Structure, electricity, sanitation, egress and hidden ceiling work stay red until verified.

02

Furniture can wait.Use a real mattress, portable fans and folding furniture while the couple learns the space.

03

No silent assumptions.Old geometry, ceiling-fan positions and the neutral-wire status are explicitly unresolved.

Do this before shopping

Today’s control panel

The fastest path is one fresh site walkthrough, eight couple decisions and four phone calls—not an open-ended online hunt.

Carlo + fiancée · 45 minutes

Freeze the household plan

  1. Name exactly who sleeps there on Jul 31.
  2. Set a household-goods cap separate from renovation.
  3. Approve defaults or one alternative in Decision Room.
Open Decision Room →

Omar · before anything is covered

Establish current site truth

  1. Timestamped walkthrough and A1–A18 status.
  2. List dirty work continuing after Jul 29.
  3. Freeze ceiling closure pending Carlo’s release.
Copy the Viber brief →

No-go means no overnight occupancy

10 hard gates

Tick a gate only after the named evidence exists. If one required gate remains red on July 31, stage delivered goods in a clean locked room and keep the current sleeping arrangement.

0/9cleared

Timestamped walkthrough: ceiling, every room, both baths, kitchen, panel, locks, roof/leak areas and remaining work.

The last verified project snapshot is Jul 23. Shopping cannot prove the house is occupiable.

Written or recorded confirmation that the removed bedroom partition was non-load-bearing, or remediation complete.

No temporary bridge. This is the documented structural unknown.

Every hidden run, junction and blocking point photographed with a tape measure; Carlo explicitly releases board closure.

Do not close the living-room ceiling before this is green.

Walk the actual route. It does not cross an open ceiling, active tools, debris, paint or a dusty work zone.

The old floor plan cannot prove this because two walls have since been demolished.

Safe covered panel; grounding/protection; no exposed live conductors; fridge and counter circuits identified; outlets and lights tested under normal load.

Physically verify neutral wires at every switch box—the records conflict.

At least one toilet flushes; one sink and shower run and drain; no active leaks; water pressure checked.

Run every fixture long enough to expose slow drains or leaks.

No active leak or unsafe overhead condition in occupied areas; roof inspected before any coating.

Rain is plausible this week. Protect appliance and mattress deliveries from moisture.

Sanding, cutting and painting finished in accessible occupied areas; tools, chemicals and debris removed; deep-clean and ventilation complete.

Do not deliver mattresses or soft goods into active construction dust.

Working locks; openable keyed bedroom grille; smoke alarms after dust/paint; kitchen heat alarm; charged extinguisher; exit lighting.

Alarms installed before dusty work will nuisance-trigger and can be damaged.

Stair gates, non-climbable balusters ≤10 cm, outlet and corner protection, safe chemical storage and a dedicated baby monitor.

Required only if Manu is part of the first move. Do not silently assume a nursery room.

Keep visible

Three unresolved project conflicts

Ceiling fans

One plan requires living/dining provisions; a later lighting note says no living fan. Install fan-rated provisions while open; actual fans remain undecided.

Neutral wires

Renovation memory says complete; technical A3 is unticked. An electrician must physically verify every switch box.

CCTV positions

The referenced plan is missing. Locate or rebuild positions before cable runs; this does not block buying household goods.

Recommended choice first

The couple’s 8 decisions

Each card has one default, at most two alternatives, a deadline and the consequence of delay. A changed choice resets both agreement checks.

0 agreed8 open

Decision 01 · Decide today

Who moves first?

Adults first

The household files mention Manu, but they do not say whether Manu moves on Jul 31. The conservative default protects the deadline without weakening child safety.

If delayed: If unresolved, plan for adults first and keep the Manu gate red.

Household goods only

A live, editable buying plan

The basket keeps verified listings separate from estimates. Delivery, installation and stock must be reconfirmed before payment; prices were checked July 25.

Horizon buttons reset the basket to recommended defaults. You can then add or remove any line.

Selected household basket

₱106,88423 lines · 27 units

₱64,005 current product listings · ₱42,879 bundles/allowances

Where the selected money goes

Kitchen₱27,079Safety₱20,394Sleep₱16,920Furniture₱8,397Cleaning₱8,200Cooling₱6,597Food & water₱6,000
Separate cap

Do not mix this with renovation money.

The project’s rough technology-only roll-up is ₱215,000–₱355,000 and material spending is not fully logged. This household basket is a different ledger.

Recommended rule: one card/account for household purchases; every receipt photographed and logged the same day.

AddItem / decisionTimingPriceSource
P1SleepQueen mattress + temporary base

G2G Premium Memory Spring queen + measured simple base.

Why / alternative / check

Why: Permanent comfort, temporary aesthetics.

Alternative: Test and buy an in-stock medium-firm queen at Uratex Miller.

Before buying: Confirm occupied room, mattress size and delivery path first.

Move-in coreOrder Jul 26₱13,420Live priceMandaue Foam Quezon AveCheck listing ↗
P1SleepMattress protector + two linen sets + 2 pillows

Washable protector; two complete sets so one can be laundered.

Why / alternative / check

Why: Keeps the new mattress usable through a messy move.

Alternative: One set now and one in week one.

Move-in coreJul 29₱3,500AllowanceDepartment store / UratexConfirm locally
P1Cooling16-inch stand fans

3D Blue Stream: common area + each occupied bedroom.

Why / alternative / check

Why: Fast, portable bridge while permanent fan positions remain disputed.

Alternative: Asahi PF-631 at ₱2,500 each.

Before buying: Does not resolve ceiling-fan locations.

Move-in coreCollect Jul 29₱6,5973 × ₱2,199 · Live priceAnson'sCheck listing ↗
P1KitchenNo-frost inverter refrigerator

Hisense RT266N2PS2N, 7.2 cu ft.

Why / alternative / check

Why: Enough for the first household without oversizing before measurements.

Alternative: Fujidenzo 6.5 cu ft ₱14,498; Panasonic 9.5 cu ft ₱24,999.

Before buying: Verify footprint, door swing, delivery path and wall outlet.

Move-in coreReserve Jul 26₱14,995Live priceAnson'sCheck listing ↗
P1KitchenInfrared cooker + rice cooker + kettle

Imarflex infrared + 3D 8-cup rice cooker + 3D 1.8 L kettle.

Why / alternative / check

Why: Three small appliances cover most first-week meals.

Alternative: Prepared-food bridge until the circuit is cleared.

Before buying: Verified wall outlets only; no high-draw appliance on an extension.

Move-in coreJul 28₱4,906Live priceAnson'sCheck listing ↗
P1Kitchen6-piece stainless cookware set

IKEA 365+ 6-piece set; works on all cooktops.

Why / alternative / check

Why: One coherent set prevents duplicate pan purchases.

Alternative: ANNONS 5-piece set at ₱699 for the leanest bridge.

Move-in coreOrder Jul 26₱1,999Live priceIKEACheck listing ↗
P1KitchenTableware starter basket for 4–6

OFTAST plates/bowls, cutlery, glasses, mugs and food containers.

Why / alternative / check

Why: A small matched basket is cheaper and easier than piecemeal buying.

Alternative: Buy four place settings first.

Move-in coreOrder Jul 26₱2,679Bundle estimateIKEACheck listing ↗
P1KitchenKnife, boards, utensils, opener, colander and towels

One chef's knife, one paring knife, two color-coded boards and only essential tools.

Why / alternative / check

Why: Completes the cooking path without buying specialty gadgets.

Alternative: Pre-packed starter kit.

Move-in coreJul 29₱2,500AllowanceIKEA / SM StoreConfirm locally
P1FurnitureFolding table + two folding chairs

One GUNDE folding table-and-two-chair set.

Why / alternative / check

Why: Functional now; permanent dining set waits for verified circulation.

Alternative: Four chairs for ₱5,296 total.

Move-in coreOrder Jul 26₱3,397Live priceIKEACheck listing ↗
P1Food & waterSealed drinking water + dispenser/pump

Two sealed containers plus a manual or rechargeable pump.

Why / alternative / check

Why: Do not assume tap water is ready for drinking.

Alternative: Bottled-water bridge.

Move-in coreJul 30₱1,000AllowanceLocal water stationConfirm locally
P1BathroomBathroom starter basket

4 towels, bath mats, shower curtain if needed, tissue, toiletries and toilet brushes.

Why / alternative / check

Why: Makes one verified bathroom fully usable on night one.

Alternative: Split by bathroom only after confirming which bath works.

Move-in coreJul 29₱4,500AllowanceSM Store / supermarketConfirm locally
P1CleaningPost-construction cleaning kit

HEPA-capable vacuum rental/service plus broom, mop, buckets, rags and cleaners.

Why / alternative / check

Why: Ordinary housekeeping is not enough for sanding and construction dust.

Alternative: Book a post-construction cleaning crew for Jul 30.

Before buying: Cleaning begins only after dirty work stops.

Move-in coreJul 29₱5,000AllowanceACE / supermarketConfirm locally
P1CleaningTrash bins, bags, hamper, hangers and drying rack

Lidded kitchen bin; smaller bath bins; one hamper; folding rack.

Why / alternative / check

Why: Supports a washer-free first week and keeps construction waste separate.

Alternative: Use labeled lidded utility bins temporarily.

Move-in coreJul 29₱3,200AllowanceIKEA / ACE / supermarketConfirm locally
P1LaundryTwo-week laundry-service bridge

Use pickup/delivery if available; keep a 14-day allowance.

Why / alternative / check

Why: Removes washer installation from the six-day critical path.

Alternative: Self-drop-off near the house.

Move-in coreBook Jul 30₱1,500AllowanceNearby laundry serviceConfirm locally
P0Safety2 × 2 kg ABC fire extinguishers

Anzen ABC 2 kg; one near the kitchen exit and one on the bedroom side, subject to the egress walk.

Why / alternative / check

Why: Immediate first-night fire response.

Alternative: Equivalent certified ABC unit from an authorized retailer.

Move-in coreJul 29₱3,1982 × ₱1,599 · Live priceACE HardwareCheck listing ↗
P0Safety4 wireless-interlinked smoke alarms

4 × X-Sense XS01-WR at the current listed unit price.

Why / alternative / check

Why: Matches the project safety plan.

Alternative: A complete certified interlinked set from a fire-safety supplier.

Before buying: Install only after dust and paint are finished.

Move-in coreInstall Jul 30₱13,196Live priceACE HardwareCheck listing ↗
P0SafetyCompatible kitchen heat alarm

Use a certified heat alarm compatible with the selected alarm approach.

Why / alternative / check

Why: The project plan calls for heat—not smoke—detection in the kitchen.

Alternative: Ask the alarm supplier for a complete four-smoke-plus-one-heat quote.

Before buying: Do not mix ecosystems without confirming interlink compatibility.

Move-in coreConfirm + install Jul 30₱1,500AllowanceFire-safety specialistConfirm locally
P0SafetyFirst-aid kit + two flashlights

Complete home kit, spare batteries and emergency contacts.

Why / alternative / check

Why: Useful during both move-in and power interruption.

Alternative: Assemble from verified components.

Move-in coreJul 29₱2,500AllowanceWatsons / ACEConfirm locally
P1ElectricalSurge-protected extension cords

AKARI 6-gang, 3 m; for electronics and lamps only.

Why / alternative / check

Why: Controlled low-load power distribution while furniture positions settle.

Alternative: Equivalent Panther or Omni certified model.

Before buying: Never use for fridge, cooker, kettle, microwave, washer or aircon.

Move-in coreJul 29₱1,2982 × ₱649 · Live priceACE HardwareCheck listing ↗
P1ConnectivityFiber order + phone-hotspot bridge

Fiber Prepaid order; use existing phone data while waiting.

Why / alternative / check

Why: Fiber lead time is longer than the move-in window.

Alternative: Globe 5G WiFi only after an on-site signal test.

Move-in coreOrder Jul 25₱999Live pricePLDTCheck listing ↗
P1FurnitureTemporary bedroom privacy

Measured ready-made blackout curtains or temporary blinds.

Why / alternative / check

Why: Privacy and sleep quality without committing to motorized treatments.

Alternative: Opaque temporary film only where egress is unaffected.

Before buying: Do not order from old plan dimensions.

Move-in coreMeasure Jul 27₱5,000AllowanceIKEA / local curtain shopConfirm locally
P1Food & waterFirst 3–4 days of food and household consumables

Simple cold storage, breakfast, rice, easy meals and sanitation supplies.

Why / alternative / check

Why: Avoids a large grocery run during final site checks.

Alternative: Prepared-food bridge.

Move-in coreJul 30₱5,000AllowanceSupermarketConfirm locally
P1LogisticsDelivery, assembly and contingency buffer

Hold as cashless payment capacity; release only against receipts.

Why / alternative / check

Why: Six-day schedules fail on small logistics costs, not just product cost.

Alternative: Store pickup if deliveries slip.

Move-in coreReserve now₱5,000AllowanceBudget reserveConfirm locally
P2Laundry8 kg automatic washer

LG T2108NT1G top load.

Why / alternative / check

Why: Useful, but laundry service removes it from the critical path.

Alternative: Fujidenzo 8 kg front load at ₱17,998.

Before buying: Verify footprint, water, drain and outlet first.

First weekAfter hookup check₱11,995Live priceAnson'sCheck listing ↗
P2Kitchen20 L microwave

LG 20 L NeoChef.

Why / alternative / check

Why: Convenient, but rice cooker and infrared cooker cover move-in night.

Alternative: American Home 20 L at ₱3,199.

First weekAug 1–7₱4,395Live priceAnson'sCheck listing ↗
P2SleepSecond-room sleep kit

Buy only for a confirmed occupant and verified room size.

Why / alternative / check

Why: “Beds” cannot be sized safely until first-night occupants are named.

Alternative: Folding guest mattress temporarily.

Before buying: Do not label the small bedroom as a nursery without confirmation.

First weekAfter occupant decision₱8,500AllowanceUratex / Mandaue FoamConfirm locally
P2StorageLidded bins + basic drawers

Temporary modular storage; keep sightlines and exits clear.

Why / alternative / check

Why: Defers new cabinetry until living patterns are known.

Alternative: Use verified existing closets first.

First weekAug 1–7₱6,000AllowanceIKEA / SM StoreConfirm locally
P0SafetyStair gates, outlet/corner protection + monitor

Hardware-mounted stair gates where suitable; dedicated baby monitor.

Why / alternative / check

Why: The four split-level steps and construction context create child-specific risks.

Alternative: Delay Manu's occupancy until the full layer is installed.

Before buying: Required before Manu sleeps at the house.

First weekBefore Manu moves₱9,500AllowanceBaby store / hardwareConfirm locally
P2Food & waterDrinking-water filtration

Choose only after water quality and under-sink space are checked.

Why / alternative / check

Why: Permanent system depends on actual water condition and cabinet space.

Alternative: Continue sealed water delivery.

First weekAfter water test₱4,000AllowanceAppliance / water specialistConfirm locally
P3FurniturePermanent master bed frame

Warm minimalist, breathable slat base, compatible exact mattress size.

Why / alternative / check

Why: Aesthetic and dimensional choice—no reason to rush it.

Alternative: Keep the temporary base longer.

Month oneAfter living in₱14,000AllowanceCouple's chosen retailerConfirm locally
P3FurniturePermanent sofa

Tape the footprint in the actual 53 m² open space first.

Why / alternative / check

Why: One of the largest visual and circulation commitments.

Alternative: Use folding chairs longer.

Before buying: Do not infer placement from the obsolete kitchen walls.

Month oneAfter circulation test₱30,000AllowanceTo be selectedConfirm locally
P3FurniturePermanent dining set

Select after living with the folding setup and measuring clearances.

Why / alternative / check

Why: The open-plan room should be experienced before fixing its zones.

Alternative: Keep the folding set.

Month oneAfter circulation test₱20,000AllowanceTo be selectedConfirm locally
P3FurniturePermanent curtains / blinds

Warm neutral, layered privacy and blackout only where needed.

Why / alternative / check

Why: Custom dimensions and style deserve a separate decision.

Alternative: Continue temporary treatments.

Month oneAfter exact measure₱20,000AllowanceCurtain specialistConfirm locally
P3ElectronicsTV / entertainment allowance

Wait for the C4 TV-wall decision and actual viewing distance.

Why / alternative / check

Why: Not a move-in need and placement affects irreversible wiring.

Alternative: No TV during the first month.

Month oneAfter TV-wall decision₱20,000AllowanceAppliance retailerConfirm locally
P0 Safety / irreversibleP1 First-night needP2 First-week functionP3 Permanent comfort / décor

One consolidated run

Buying and delivery route

Reserve by phone first, ask for an exact delivery date to the QC address, and use store pickup as the fallback. A website’s “in stock” badge is not a delivery promise.

A

Appliances · call first

Anson’s Trinoma

Reserve fridge, three fans and small cooking appliances together. Ask for unit serials, delivery date, warranty and inspection-on- receipt process.

Branch details ↗
B

Sleep · test / confirm stock

Quezon Avenue mattress stop

Mandaue Foam: 55 Quezon Ave cor. BMA. Uratex fallback: 32 Miller St., Bungad. Do not mix a 60×75-inch mattress with a 150×200-cm IKEA frame.

Mandaue stores ↗
C

Kitchen + folding furniture

IKEA Trinoma Click & Collect

Submit the cookware, tableware and folding-set basket by Jul 26. The official collection page states a 2–3 day Trinoma lead.

Collection details ↗
D

Safety + cleaning

ACE / nearby supermarket

Buy extinguisher, alarms, first aid, cleaning and bath consumables. Install alarms only after dusty work and paint are finished.

Alarm listings ↗
Accept deliveries only after four checks:correct modelno visible damagecomplete accessoriesinvoice + warranty photographed

July 25 → July 31

The seven-day runbook

Measurements precede orders; dirty work precedes cleaning; safety devices precede soft goods; the final walkthrough precedes occupancy.

1

Sat · Jul 25

Freeze + establish truth

Today
  • Declare Jul 31 a conditional first night; freeze ceiling closure.
  • Get Omar's timestamped walkthrough and A1–A18 status.
  • Name the first-night occupants; order fiber; book Monday checks.
  • Set separate caps for renovation readiness and household goods.
2

Sun · Jul 26

Couple decision + order day

Cutoff
  • Measure sleeping room, delivery path, fridge space/outlet and curtain spans.
  • Reserve only confirmed in-stock items deliverable by Jul 29–30.
  • Order mattress, fridge, fans, starter kitchen and folding furniture.
  • Book post-construction cleaning for Jul 30.
3

Mon · Jul 27

Site truth day

Gate 1
  • Structural, roof/weather, electrical and plumbing checks.
  • Physically verify neutral wires at every switch box.
  • Walk the occupied bedroom → bath → exit route.
  • Any unresolved critical issue turns Jul 31 red until cleared.
4

Tue · Jul 28

Irreversible work + A15

No shortcuts
  • Finish A1–A18 and the fan-rated provisions/blocking.
  • Photograph every hidden run and blocking point with tape measure.
  • Carlo reviews the archive; only then release board closure.
  • Keep mattresses and soft goods away from dust.
5

Wed · Jul 29

Dirty work ends

Stop line
  • Finish ceiling closure plus all sanding, cutting and high-fume work.
  • If dirty work cannot stop, family occupancy on Jul 31 becomes no-go.
  • Confirm every delivery, installer and receiving contact.
  • Verify and log the normal Wednesday crew vale.
6

Thu · Jul 30

Clean, install, rehearse

Gate 2
  • Deep-clean and ventilate; no sanding or painting afterward.
  • Install alarms; receive bed, fridge, fans and starter kits.
  • Load-test power; run water/drains; test locks, exits and cooking.
  • Couple performs a first-night rehearsal and closes every red gate.
7

Fri · Jul 31

Final verdict + staged move

Move / hold
  • Both partners sign the gate sheet.
  • Amber comfort items may use documented bridges.
  • Any red safety gate means no overnight occupancy; stage goods only.
  • If green, move essentials first and keep them separate from crew materials.

What “moved in” actually means

First-night rehearsal

Do this together on July 30, after cleaning. A pass means the house works for one ordinary evening and one emergency exit—not that the renovation is complete.

01

Arrive after dark

Unlock gate and door; walk the exit route with normal lighting and one flashlight.

02

Use the bathroom

Flush, shower, run sink, watch drains and check for leaks or slippery paths.

03

Run normal loads

Fridge, lights and one cooking appliance operate on their verified circuits without heat, smell or trips.

04

Prepare one meal

Cook, wash up, manage waste and confirm safe drinking water—without an extension on high-draw appliances.

05

Sleep environment

Clean mattress and linen, privacy, fan stability, phone charging and smoke/heat alarms all ready.

06

Emergency exit

Both adults can open locks and the keyed bedroom grille; keys and extinguisher are visible and reachable.

Copy-paste Viber brief

Omar’s site command

This keeps the move-in deadline direct while preserving the ceiling, neutral-wire and geometry warnings already in the project record.

Viber · Omar1810 characters
Omar, target natin ang conditional first night sa bahay on Friday, July 31. Hindi ibig sabihin tapos na lahat—kailangan lang safe, malinis, may working na tulugan, banyo, tubig, kuryente at exit.

PAKI-SEND TODAY:
1. Isang timestamped video walkthrough: living ceiling, bawat room, both bathrooms, kitchen/sink, electrical panel, locks/grilles, roof/leak areas, at lahat ng natitirang trabaho.
2. Status ng A1–A18, one line bawat item: DONE / NOT DONE / BLOCKER, with photo/video.
3. Listahan ng anumang sanding, cutting, pintura o maalikabok na trabaho na aabot after July 29.

IMPORTANT:
• HUWAG muna isara ang living-room ceiling hangga't hindi complete ang A1–A18 at A15 photos. Lahat ng hidden runs, junctions at blocking dapat may picture na may tape measure. Ako ang magbibigay ng explicit GO bago mag-board.
• Paki-physically verify ang neutral wire sa BAWAT switch box. Conflict ang records, so huwag i-assume na done.
• Sa ceiling fans: ilagay ang fan-rated boxes/blocking/provisions per plan habang open pa, pero pending pa ang final decision sa actual living-room fan. Huwag i-resolve nang kusa.
• Paki-confirm sino ang qualified na mag-check Monday ng demolished partition, roof/leaks, electrical safety at water pressure/drainage.

BY JULY 30, kailangan ma-test:
• safe at covered ang panel; walang exposed live wire
• identified at tested ang fridge at kitchen counter circuits
• at least 1 toilet, 1 sink at 1 shower working at draining, no leaks
• clear at safe ang route bedroom → bathroom → exit
• tapos na ang sanding/cutting/painting; tanggal tools, chemicals at debris
• working locks at openable keyed bedroom grille

Reply per item with DONE / NOT DONE / BLOCKER + photo/video. Kapag may red safety item sa July 31, hindi muna kami matutulog doon kahit na-deliver na ang gamit. Salamat.

Audit trail

Assumptions, price confidence and sources

The dashboard distinguishes project facts, current retailer listings and planning allowances. Nothing has been purchased, reserved or transmitted to a retailer.

Project fact

House and renovation state

The local project files govern geometry, status, money and irreversible work. Last site snapshot: Jul 23. The 53 m² open-plan room and the two retained bedroom ceilings guide only broad strategy—not furniture placement.

Current listing

Price and stock

“Live price” means the product page was checked Jul 25. Stock and promotion badges can change; call the branch and get an exact delivery or pickup commitment before paying.

Planning allowance

Not a quote

Linens, cleaning, bath, logistics and permanent furniture use round planning allowances. Replace them with receipts or written quotes as purchases happen.

Weather note

Keep goods dry

PAGASA’s Jul 24 weekly outlook allows for rain in Metro Manila during the window. Roof/leak checks and covered delivery staging remain ahead of mattresses and appliances.